General Decision Number: WV120008 01/20/2012 WV8 Superseded General Decision Number: WV20100010 State: West Virginia Construction Type: Heavy Counties: Boone, Brooke, Cabell, Clay, Fayette, Greenbrier, Hancock, Kanawha, Lincoln, Logan, Marshall, McDowell, Mercer, Mingo, Monroe, Nicholas, Ohio, Pocahontas, Putnam, Raleigh, Summers, Wayne, Wood and Wyoming Counties in West Virginia. HEAVY CONSTRUCTION PROJECTS Modification Number Publication Date 0 01/06/2012 1 01/13/2012 2 01/20/2012 BRWV0001-002 07/01/2010 MARSHALL and OHIO COUNTIES Rates Fringes BRICKLAYER All refactory work..........$ 30.72 14.29 Includes acid brick or acid resistant materials or any brick, block, stone, ceramic tile, or marble masonry in an industrial facility.........$ 27.97 14.29 ---------------------------------------------------------------- BRWV0005-003 06/01/2011 CABELL, LINCOLN, MINGO, AND WAYNE COUNTIES Rates Fringes Bricklayer, Stonemason...........$ 28.68 17.86 ---------------------------------------------------------------- BRWV0006-004 06/01/2011 WOOD COUNTY Rates Fringes Bricklayer, Stonemason...........$ 27.67 13.70 ---------------------------------------------------------------- BRWV0009-003 12/01/2010 BOONE, CLAY, FAYETTE, GREENBRIER, KANAWHA, LOGAN, MCDOWELL, MERCER, MONROE, NICHOLAS, PUTNAM, RALEIGH, SUMMERS, and WYOMING COUNTIES Rates Fringes Bricklayer, Stonemason, Pointer, Caulker & Cleaner.......$ 27.79 16.64 ---------------------------------------------------------------- BRWV0011-002 07/01/2010 BROOKE and HANCOCK COUNTIES Rates Fringes BRICKLAYER All refractory work, acid brick or acid resistant materials or any brick, block, stone, ceramic tile or marble masonry in an industrial facility.........$ 30.63 15.03 ---------------------------------------------------------------- * BRWV0015-003 12/01/2011 POCAHONTAS COUNTY Rates Fringes Bricklayer, Stonemason...........$ 28.16 15.42 ---------------------------------------------------------------- CARP0003-007 12/01/2011 BROOKE, HANCOCK, MARSHALL (North of 39 degrees 46' latitude), and OHIO COUNTIES Rates Fringes CARPENTER........................$ 24.94 13.78 ---------------------------------------------------------------- CARP0302-002 06/01/2011 CABELL, MINGO, and WAYNE COUNTIES Rates Fringes CARPENTER........................$ 28.84 16.50 Pile Driver......................$ 29.25 16.50 ---------------------------------------------------------------- CARP0604-004 12/01/2011 POCAHONTAS COUNTY Rates Fringes Carpenter & Soft Floor Layer Including Drywall Hanging...$ 27.41 14.24 ---------------------------------------------------------------- CARP0899-005 12/01/2011 WOOD and MARSHALL (South of 39 degrees 46' latitude) COUNTIES Rates Fringes CARPENTER........................$ 26.03 16.11 ---------------------------------------------------------------- CARP1207-001 12/01/2011 BOONE, CLAY, KANAWHA, LINCOLN, LOGAN, NICHOLAS, and PUTNAM COUNTIES Rates Fringes CARPENTER........................$ 28.48 15.40 Pile Driver......................$ 28.73 15.40 ---------------------------------------------------------------- CARP1911-002 12/01/2011 FAYETTE, GREENBRIER, McDOWELL, MERCER, MONROE, RALEIGH, SUMMERS, and WYOMING COUNTIES Rates Fringes CARPENTER........................$ 28.48 15.40 Pile Driver......................$ 28.73 15.40 ---------------------------------------------------------------- CARP2235-011 12/01/2009 BROOKE, HANCOCK, MARSHALL, and OHIO COUNTIES Rates Fringes Pile Driver......................$ 29.95 12.17 ---------------------------------------------------------------- ELEC0071-016 01/03/2011 BROOKE (EXCEPT BUFFALO TOWNSHIP) and HANCOCK COUNTIES Rates Fringes Line Construction: Equipment operator..........$ 28.13 11.25 Groundman...................$ 20.31 11.25 Lineman & Cables Splicers...$ 31.25 11.25 ---------------------------------------------------------------- ELEC0141-004 09/05/2011 BROOKE (Buffalo Twp. only), MARSHALL and OHIO COUNTIES Rates Fringes CABLE SPLICER....................$ 28.61 20.72 ELECTRICIAN......................$ 30.01 21.25 ---------------------------------------------------------------- ELEC0141-006 09/05/2011 BROOKE (Buffalo Twp. only), MARSHALL and OHIO COUNTIES Rates Fringes Line Construction: Cable Splicer...............$ 28.61 20.72 Groundman...................$ 28.61 20.72 Lineman & Equipment Operator....................$ 28.61 20.72 ---------------------------------------------------------------- ELEC0246-007 10/31/2011 BROOKE (Except Buffalo Township) and HANCOCK COUNTIES Rates Fringes ELECTRICIAN......................$ 33.00 24.51+a FOOTNOTE: a. 1 1/2 Paid Holidays: The last scheduled workday prior to Christmas & 4 hours on Good Friday. ---------------------------------------------------------------- ELEC0317-010 09/05/2011 BOONE, CABELL, CLAY, FAYETTE, KANAWHA, LINCOLN, LOGAN, MINGO, NICHOLAS, PUTNAM, RALEIGH, SUMMERS, WAYNE , and WYOMING COUNTIES Rates Fringes Line Construction: Cable Splicer...............$ 32.31 19.75%+7.11 Equipment Mechanic..........$ 22.87 19.75%+7.11 Equipment Operator A: John Henry Rock Drill, D6 (or equivalent) and above, Trackhoe Digger, & Cranes (greater than 25 tons and less than 45 tons)..........$ 27.31 19.75%+7.11 Equipment Operator B: Cranes (6-25 tons), Backhoes, Road Tractor, Dozer up to D5, Pressure Digger-Wheeled or Tracked, & all Tension Wire Stringing Equipment.........$ 23.87 19.75%+7.11 Equipment Operator C: Trencher, Vibratory Compactor, Ground Rod Driver, Boom Truck (6 ton or below), & Skid Steer Loaders.....................$ 18.76 19.75%+7.11 Groundman/Truck Driver......$ 15.69 19.75%+7.11 Line Truck w/Auger..........$ 20.97 19.75%+7.11 Lineman & Technician........$ 30.74 19.75%+7.11 All operators of 45 ton cranes or larger shall be paid the journeyman lineman's rate of pay. ---------------------------------------------------------------- ELEC0317-011 09/05/2011 CABELL, LINCOLN, LOGAN, MINGO AND WAYNE COUNTIES Rates Fringes Electricians: Cable Splicers..............$ 32.31 19.75%+7.11 Electricians................$ 31.87 19.93 ---------------------------------------------------------------- ELEC0466-002 06/01/2011 BOONE, CLAY, FAYETTE, KANAWHA, NICHOLAS, PUTNAM, RALEIGH, SUMMERS, and WYOMING COUNTIES Rates Fringes CABLE SPLICER....................$ 37.88 15.03 ELECTRICIAN......................$ 34.44 15.03 ---------------------------------------------------------------- ELEC0637-003 06/01/1998 GREENBRIER, MCDOWELL, MERCER, MONROE AND POCAHONTAS COUNTIES Rates Fringes Line Construction: Cable Splicer...............$ 20.31 3.80+3.5% Equipment Operator..........$ 11.04 3.80+3.5% Groundman & Truck with winch.......................$ 10.82 3.80+3.5% Lineman.....................$ 19.34 3.80+3.5% ---------------------------------------------------------------- ELEC0637-004 06/01/2003 GREENBRIER, MCDOWELL, MERCER, MONROE AND POCAHONTAS COUNTIES Rates Fringes ELECTRICIAN......................$ 18.31 5.80+1.5% ---------------------------------------------------------------- ELEC0968-004 06/01/2011 WOOD COUNTY Rates Fringes ELECTRICIAN......................$ 30.14 19.26 ---------------------------------------------------------------- ELEC0968-005 06/01/2011 WOOD COUNTY Rates Fringes Line Construction:...............$ 30.14 19.26 Cable Splicer, Equipment Operator, Groundman, and Lineman.....................$ 30.14 19.26 ---------------------------------------------------------------- ENGI0132-002 12/01/2011 Rates Fringes Power equipment operators: GROUP 1.....................$ 31.00 16.30 GROUP 2.....................$ 28.24 16.30 GROUP 3.....................$ 27.13 16.30 GROUP 4.....................$ 23.67 16.30 POWER EQUIPMENT OPERATOR CLASSIFICATIONS GROUP 1: Class I shall include those operating the following equipment: cranes, tower cranes, derricks, derrick boats, dredge, draglines, clamshells, cableways, boom trucks, loaders of six (6) cubic yard capacity and over, excavators and shovels with an operating weight of one hundred ten thousand (110,000) pounds and over. GROUP 2: Class II shall include those operating the following equipment: loaders up to six (6) cubic yard capacity, gradall, hoist (two drums or more), mixer plant (two or more mixers includiing batch control), pile driver, trencher, backhoe, asphalt paver, cement paver, rotary drill, bulldozers, standard gauge locomotive, concrete pump, controlled fine grade machine, slip form paver, log loader, log skidder, motor grader, rubber tired scraper, tractor pan, Roto Miller, tow or work boat, mobile conveyor, transloader, articulating equipment, material hauler, carry deck, compactor with blade, skidsteer including attachments, fork lift, self-propelled concrete spreader, concrete finishing machine, derrick (single drum), hoist (single drum), single drum paver, air tugger, Ross Carrier, multiple concrete saw, hydraulic post driver, horizontal road-boring machine, tie distributor, track lining machine, ballast tamper, anchor application machine, ribbon rail puller, ballast regulator, auto sled, turn table, pavement breaker, asphalt batch plant, concrete batch plant, crushing plant, compactor with blade, power broom, vac-all truck, self-propelled concrete spreader and concrete finishing machine, mechanics with tools greasers. Class II shall also include excavators, and shovels with an operating weight of up to one hundred ten thousand (110,000) pounds. GROUP 3: Class III shall include those operating the following equipment: Asphalt roller. GROUP 4: Class IV shall include those operating the following type of equipment: air compressor, concrete mixer (under one (1) cubic yard), light plant, narrow gauge locomotive, fireman, mechanic's tender, assistant engineer, deckhand, screed man, spreader box man, joint sealer and pump, steam jenny, stationary conveyor (belt or bucket), gasoline or diesel powered welder, brakeman of locomotive, conductor of locomotive, A-frame tire man, screening and washing plant, form subgrader, power form handling equipment, burlap and curing machine, form grader, bull float, bar and joint installing machine, roller and compactor, hydroblaster, concrete mixer (single drum, one (1) cu. yd. or over), portable concrete saw and highway striping operator. Utility operators shall be paid Class II rate when operating more than one (1) but less than five (5) air compressors, pumps, stationary conveyors (belt or bucket), light plants, and gasoline or diesel powered welder, brakeman of locomotive conductor or locomotive, A-frame tire man, screening and washing plant, form subgrader, power form handling equipment, burlap and curing machine, form grader, bull float, bar and joint installing machine, roller and compactor, hydroblaster, concrete mixer (single drum, one (cu. yd. or over), portable concrete saw and highway stripping operator. Utility operators shall be paid Class II rate when operating more than one (1) but less than five (5) air compressors, pumps, stationary conveyors (belt or bucket), light pants, and gasoline or diesel powered welders. A. Classes shall be paid the following rates for the years 2004 through and including 2006 as long as those rates are the prevailing rates for the respective years: B. Operators operating excavators and endloaders of one and one-half (1 1/2) cu. yd. capacity to, and including, three (3) cu. yd. capacity shall receive an additional $1.05 per hour worked above the Class II Rate. Operators operating excavators and endloaders from three (3) cu. yd. capacity to six (6) cu. yd. capacity shall receive an additional $1.35 per hour worked above this Class II Rate. Operators required to have an Electricians License will receive an additional $1.00 per hour. C. Capacities for equipment shall be as per manufacturers maximum rated capacity. D. $0.25 per hour shall be added to all of the above schedules for tunneling and for all other underground work. Footnote: (Hazardous/toxic waste material handling - wages for employees working in direct contact with a hazardous/toxic waste material which is classified level A or level B by the U.S. Environmental Protection Agency and who are required to wear personal protective equipment for respiratory, skin or eye protection for that level of work, shall be $.50 above the appropriate classification rate). ---------------------------------------------------------------- IRON0301-002 06/01/2011 BOONE, CLAY, FAYETTE, KANAWHA, LINCOLN, LOGAN, MCDOWELL, MINGO, NICHOLAS, PUTNAM, RALEIGH, and WYOMING COUNTIES Rates Fringes IRONWORKER.......................$ 31.93 17.17 ---------------------------------------------------------------- IRON0549-005 12/01/2011 BROOKE, HANCOCK, MARSHALL, AND OHIO COUNTIES Rates Fringes IRONWORKER.......................$ 33.56 16.04 ---------------------------------------------------------------- IRON0697-004 12/01/2009 GREENBRIER, MERCER, MONROE, POCAHONTAS, and SUMMERS COUNTIES Rates Fringes IRONWORKER.......................$ 31.55 11.43 ---------------------------------------------------------------- IRON0769-006 12/01/2011 CABELL and WAYNE COUNTIES Rates Fringes IRONWORKER.......................$ 32.74 18.83 ---------------------------------------------------------------- IRON0787-005 12/01/2010 WOOD COUNTY Rates Fringes IRONWORKER.......................$ 30.67 17.05 ---------------------------------------------------------------- LABO0379-004 12/01/2011 BOONE, BROOKE, CABELL, CLAY, FAYETTE, GREENBRIER,HANCOCK, KANAWHA, LINCOLN, LOGAN, MCDOWELL, MARSHALL, MERCER, MINGO, MONROE, NICHOLAS, OHIO, POCAHONTAS, PUTNAM, RALEIGH, SUMMERS, WAYNE, WOOD, and WYOMING COUNTIES Rates Fringes Laborers: GROUP 1.....................$ 25.85 13.25 GROUP 2.....................$ 24.82 13.25 GROUP 3.....................$ 23.76 13.25 LABORER CLASSIFICATIONS GROUP 1: Blacksmith, Tunnel Driller, Tunnel Miner, Powderman, Mucker-Chucker, Reinforcing Bar Handler (Structures), Toxic and Hazardous Waste Removal Laborer, Asbestos Abatement Laborer and Lead Base Paint Removal Laborer, Inside Laborer, Laser Screed Operator, and GPS Operator. GROUP 2: Pipelayer (Including Laser Beam Set Up), Form Setter (Road), Drill op., Air Tool op., Grade Checker and Asphalt Raker, Vibrator Man, Whacker, Chainsaw op., Mortarman, Brick Mason Tender, Blacksmith Tender, Cement Finisher Tender, Drill Tender, Powderman Tender, Water Proofer, Sheeter & Shorer, Placement of Lagging, Bull-Float Man, Pavement Reinforcing Placer, Handyman, Signal Man, Greencutter, Georgia Power Buggie, Burner, Cement Blower Man,Tree Trimmer, Deckhand, Bituminous Hand Sprayer, Bork 250 Remote Control Ditch Witch and Walk Behind Concrete Saw, Deckhand, Casion Bottom Man, Mulcher and Seeder (hand and machine), Installation of Ground Mounted Beams and Signs including Concrete Footers, Installation of Overhead sign Supports and Signs including concrete Footers, Installation of Guardrail and Anchors Assemblies, Tree Trimmer, Bush Hammering Laborer, Core Drilling Laborer, and Placement and Mixing of Grout Laborer. GROUP 3: General Laborer, Flag Person, Traffic Control Maintenance Person, Watchman, Carpenter's Tender, Pipelayer Tender, and Herbicide Sprayer. ---------------------------------------------------------------- PAIN0091-002 12/01/2011 BROOKE (SOUTH OF BUFFALO CREEK), MARSHALL,AND OHIO COUNTIES Rates Fringes Painters: (Smokestacks, Railroad and Highway Bridges, and Locks and Dams)..............$ 27.75 13.18 Painters: (Substations, Power Line Towers).....................$ 27.75 13.18 ---------------------------------------------------------------- PAIN0438-004 12/01/2010 BROOKE (NORTH OF BUFFALO CREEK) and HANCOCK COUNTIES Rates Fringes Painters: Bridges, Locks , Dams, High Tension Towers, Energized Substations, Tanks, Smokestacks, Railroad & Highway..........$ 28.33 11.40 Power Generating Facilities.$ 25.18 11.40 ---------------------------------------------------------------- PAIN0813-002 12/01/2008 CABELL, LINCOLN, LOGAN, MINGO AND WAYNE COUNTIES Rates Fringes Painters: Brush, Roller, Spray, and Sandblast...................$ 24.83 10.00 ---------------------------------------------------------------- PAIN0970-002 12/01/2011 BOONE, CLAY, FAYETTE, GREENBRIER, KANAWHA, MCDOWELL, MERCER, MONROE, NICHOLAS, POCAHONTAS, PUTNAM, RALEIGH, SUMMERS and WYOMING COUNTIES Rates Fringes Painters: Bridges; Locks; Dams; Tension Towers & Energized Substations.................$ 29.33 12.85 Power Generating Facilities.$ 26.09 12.85 ---------------------------------------------------------------- PAIN1144-004 12/01/2011 WOOD COUNTY Rates Fringes PAINTER Bridges; Locks; Dams; Tension Towers & Energized Substations.................$ 28.49 12.50 Power Generating Facilities.$ 25.34 12.50 ---------------------------------------------------------------- PLAS0002-002 12/01/2005 MCDOWELL, MERCER AND WYOMING COUNTIES Rates Fringes CEMENT MASON/CONCRETE FINISHER...$ 24.45 11.50 ---------------------------------------------------------------- PLAS0005-004 12/01/2005 MINGO COUNTY Rates Fringes CEMENT MASON/CONCRETE FINISHER...$ 25.91 11.50 ---------------------------------------------------------------- PLAS0015-001 12/01/2005 POCAHONTAS COUNTY Rates Fringes CEMENT MASON/CONCRETE FINISHER...$ 28.24 7.12 ---------------------------------------------------------------- PLAS0039-005 12/01/2009 BROOKE, HANCOCK, MARSHALL and OHIO COUNTIES Rates Fringes CEMENT MASON/CONCRETE FINISHER...$ 27.41 13.20 ---------------------------------------------------------------- PLAS0181-003 12/01/2004 WOOD COUNTY Rates Fringes CEMENT MASON/CONCRETE FINISHER...$ 25.29 8.95 ---------------------------------------------------------------- PLAS0887-002 12/01/2009 BOONE, CABELL, CLAY, FAYETTE, GREENBRIER, KANAWHA, LINCOLN, LOGAN, MERCER, MONROE, NICHOLAS, PUTNAM, RALEIGH, SUMMERS, and WAYNE COUNTIES Rates Fringes CEMENT MASON/CONCRETE FINISHER...$ 28.98 12.20 ---------------------------------------------------------------- PLUM0083-003 07/01/2011 BROOKE COUNTY (North to Route #27 due east to the State Line, Excluding the City limits of Wellsburg), MARSHALL,AND OHIO COUNTIES Rates Fringes Plumber; Steamfitter.............$ 34.41 18.18 ---------------------------------------------------------------- PLUM0495-005 06/01/2011 BROOKE (City limits of Wellsburg and north of St. Rt. 27 to the Pennsylvania State Line) and HANCOCK (Districts of Butler, Clay and the part of Grant District south of the dividing line) COUNTIES Rates Fringes Plumbers and Pipefitters.........$ 36.13 18.16 ---------------------------------------------------------------- PLUM0521-004 06/01/2011 CABELL, LINCOLN, LOGAN, MCDOWELL, MINGO, WAYNE AND WYOMING COUNTIES Rates Fringes Plumbers and Pipefitters.........$ 32.48 16.95 ---------------------------------------------------------------- PLUM0565-003 07/01/2011 WOOD COUNTY Rates Fringes Plumbers and Pipefitters.........$ 32.79 18.32 ---------------------------------------------------------------- PLUM0625-004 12/01/2011 BOONE, CLAY, FAYETTE, GREENBRIER, KANAWHA, MONROE, NICHOLAS, POCAHONTAS, PUTNAM, RALEIGH and SUMMERS COUNTIES Rates Fringes Plumbers and Pipefitters.........$ 34.79 15.93 ---------------------------------------------------------------- PLUM0625-006 12/01/2011 MERCER COUNTY Rates Fringes Plumbers and Pipefitters.........$ 34.79 15.93 ---------------------------------------------------------------- TEAM0092-002 12/01/2011 BROOKE AND HANCOCK COUNTIES Rates Fringes Truck drivers: GROUP 1.....................$ 25.47 13.71 GROUP 2.....................$ 27.22 13.71 GROUP 3.....................$ 28.01 13.71 GROUP 1: Single Axle Trucks used as Dumps, Suppy, Fuel, Water, Van , Flatbody, Monorail, Distributor (other than Bituminous Distributors) including Towed Single Units, Team 4-Up, Team 2-Up & Pick-up trucks. GROUP 2: Tandem and Tri-Axle Trucks used as Dumps, Supply, Fuel, Water, Van, Flatbody, Monorail and including Towed Single Units, Truck Tractors used in combination with Dumps, Van, Tank, Flatbed, Low platform or Pole Trailers, Bituminous Distributors, Agitators or Mixer Trucks (up to and including 20 cubic-yards), Rubber-tired tractors, (towing and pushing), Drag Drivers and Tag-alongs. GROUP 3: Off Highway Trucks, Mobile Metered Mixer, Agitator or Mixer Trucks (over 20 cubic yards), Off Highway Rear Dump Trucks, Articulating Dumps, "A" Frame & Mechanic. ---------------------------------------------------------------- TEAM0175-004 12/01/2011 BARBOUR, BOONE, BRAXTON, CALHOUN, CLAY, DODDRIDGE, FAYETTE, GILMER, GREENBRIER, KANAWHA, MCDOWELL, MERCER, MONROE, NICHOLAS, POCAHONTAS, PUTNAM, RALEIGH, SUMMERS, WOOD AND WYOMING COUNTIES Rates Fringes TRUCK DRIVER GROUP 1.....................$ 24.97 14.20 GROUP 2.....................$ 25.76 14.20 GROUP 3.....................$ 26.44 14.20 GROUP 1: Single Axle Trucks used as Dumps, Supply, Fuel, Water, Van, Flatbody, Monorail, Distributor (other than Bituminous Distributors), and including Towed Single Units, Team 4-Up, Greasers, Tireman and Mechanic Tenders (Trucks), Yardmen, Team 2-Up and pick-up trucks. GROUP 2: Tandem and Tri-Axle Trucks used as Dumps, Supply, Fuel, Water, Van, Flatbody, Monorail and including Towed Single Units, Truck Tractors used in combination with Dump, Van, Tank, Flatbed, Low Platform or Pole Tailers, Bituminous Distributors, Agitator or Mixer Trucks (up to and including 20 cubic yards), Rubber-tired Tractors (lowing and pushing), Drag Drivers and Tag-alongs. GROUP 3: Off Highway Trucks, Mobile Metered Mixer, Agitator or Mixer Trucks (over 20 cubic yards), Off Highway Trucks, Rear Dump Trucks, Articulating Dumps, "A" Frame, Mechanic (Truck). ---------------------------------------------------------------- TEAM0505-006 12/01/2011 CABELL, LINCOLN, LOGAN, MINGO AND WAYNE COUNTIES Rates Fringes Truck drivers: GROUP 1.....................$ 27.66 13.82+A GROUP 2.....................$ 28.63 13.82+A GROUP 3.....................$ 29.42 13.82+A GROUP 1: Single Axle Trucks used as Dumps, Suppy, Fuel, Water, Van , Flatbody, Monorail, Distributor (other than Bituminous Distributors) including Towed Single Units, Material Checkers & Receivers, Team 4-Up, Team 2-Up and Pick-up trucks. GROUP 2: Tandem and Tri-Axle Trucks used as Dumps, Supply, Fuel, Water, Van, Flatbody, Monorail and including Towed Single Units, Truck Tractors used in combination with Dumps, Van, Tank, Flatbed, Low platform or Pole Trailers, Bituminous Distributors, Agitators or Mixer Trucks (up to and including 20 cubic-yards), Rubber-tired tractors, (towing and pushing), Drag Drivers and Tag-alongs. GROUP 3: Off Highway Trucks, Mobile Metered Mixer, Agitator or Mixer Trucks (over 20 cubic yards), Off Highway Rear Dump Trucks, Articulating Dumps, "A" Frame, Mechanic. A. Paid Holidays: New Year's Day, Memorial Day, July 4th, Labor Day, Thanksgiving Day, Day after Thanksgiving, and Christmas Day. ---------------------------------------------------------------- TEAM0697-004 12/01/2011 MARSHALL AND OHIO COUNTIES Rates Fringes Truck drivers: GROUP 1.....................$ 24.53 14.31 GROUP 2.....................$ 25.43 14.31 GROUP 3.....................$ 26.03 14.31 GROUP 1: Single Axle Trucks used as dumps, supply, fuel, water, van, flatbody, monorail, distributor (other than Bituminous Distributors), and including towed single units, material checkers and receivers, team 4-up, greasers, tiremen and mechanic tenders (trucks), warehouse, yardmen, team 2-up John Deere gators and similar equipment. GROUP 2: Tandem axle trucks used as dump, supply, fuel, water flatbody, monorail and including towed single units, truck tractors used in combination with dump, van, tank, flatbed, low platform, or pole trailers, bituminous distributors, agitator or mixer trucks (up to and including 20 c.y.), rubber-tired tractors (towing and pushing), drag drivers, tag-alongs, passenger vans and buses. GROUP 3: Off Highway Trucks, mobile metered mixer, agitator or mixter trucks (over 20 cubic yards), off highway rear dump trucks, articulating dumps, "A" frame, mechanic (truck) and/or dispatchers ---------------------------------------------------------------- WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental. ================================================================ Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)). ---------------------------------------------------------------- The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union. Union Identifiers An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be July 1, 2011 in the above example. Union prevailing wage rates will be updated to reflect any changes in the collective bargaining agreements governing the rate. Non-Union Identifiers Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007 5/13/2010. SU indicates the rates are not union rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date. Survey wage rates will remain in effect and will not change until a new survey is conducted. ---------------------------------------------------------------- WAGE DETERMINATION APPEALS PROCESS 1.) Has there been an initial decision in the matter? This can be: * an existing published wage determination * a survey underlying a wage determination * a Wage and Hour Division letter setting forth a position on a wage determination matter * a conformance (additional classification and rate) ruling On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed. With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to: Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to: Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue. 3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to: Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 4.) All decisions by the Administrative Review Board are final. ================================================================ END OF GENERAL DECISION