General Decision Number: UT080023 05/16/2008 UT23 Superseded General Decision Number: UT20070023 State: Utah Construction Type: Highway Counties: Davis and Weber Counties in Utah. HIGHWAY CONSTRUCTION PROJECTS Modification Number Publication Date 0 02/08/2008 1 05/16/2008 ELEC0354-002 06/01/2007 Rates Fringes ELECTRICIAN......................$ 26.72 6.25+4.3% ---------------------------------------------------------------- ENGI0003-016 07/01/2007 Rates Fringes Power equipment operators: Blade smooth/finish.........$ 24.30 10.86 Tractor, small rubber tire with attachments............$ 21.78 10.86 ---------------------------------------------------------------- * IRON0027-004 07/01/2007 Rates Fringes IRONWORKER, REINFORCING..........$ 23.61 10.15 ---------------------------------------------------------------- SUUT1992-007 03/25/1992 Rates Fringes CARPENTER........................$ 16.13 2.80 CEMENT MASON/CONCRETE FINISHER...$ 14.40 2.41 Flagger..........................$ 6.59 1.75 Ironworkers: Ornamental & Structural.....$ 16.65 3.65 Laborers: Concrete Laborer (Compaction, Underground Fine Grading, Operation of Shute or Bucket)............$ 10.04 2.53 Fence Erection Laborer (clearing of right of way, unloading of materials by hand, digging of post holes & pouring of concrete in connection therewithin)................$ 10.04 2.53 General Laborer, Asphalt Raker, Landscape Laborer....$ 10.04 2.53 Grade Laborer (Uses hand held level to check grade, inserts grade stakes in concrete)...................$ 10.04 2.53 Laborer, Power Tools (Cutting Torch, Operators of Gasoline, Electric or Pneumatic Tools, e.g. compressor, compactor, jackhammer, vibrator, concrete saw, chain saw, and concrete cutting torch).$ 12.65 2.79 Pipelayer (Smooths sides and bottom of trenches, does rigging of pipe, assembles and installs concrete and tile pipe).....$ 11.03 3.54 PAINTER (Spray) SPRAY.......................$ 14.05 1.62 Power equipment operators: Asphalt Finishing Machine...$ 14.14 5.69 Asphalt Plant Operator......$ 18.05 7.23 Backhoe, Tire & Track, over 5 cu. yds..............$ 14.05 7.23 Backhoe, Tire & Track, under 5 cu. yds.............$ 13.44 4.57 Blade, Rough................$ 11.60 2.22 Bulldozer, All Sizes........$ 18.05 7.08 Chip Spreader...............$ 16.29 7.08 Laydown Machine, Asphalt/Concrete............$ 12.53 2.22 Loader, All Sizes...........$ 18.05 5.09 Paver, Asphalt..............$ 12.53 2.22 Roller, Asphalt.............$ 12.80 4.12 Roller, Grade/Compaction....$ 11.01 3.31 Screedman...................$ 10.95 3.09 Truck drivers: (Dump Trucks - Water Level Capacity (Bottom, End and Side), Including Dumpster Truck, Turnawagons, Turnarockers and Dumpcrete):) 14 cu. yds. and less than 35 cu. yds..................$ 16.14 4.87 8 cu. yds. and less than 14 cu. yds..................$ 9.80 2.22 Less than 8 cu. yds.........$ 10.50 ---------------------------------------------------------------- TEAM0222-003 07/01/2003 Rates Fringes Truck Driver - Transit Mix 0 cu. yds. to 8 cu. yds.....$ 16.415 7.52 8 1/4 cu. yds. to 14 cu. yds.........................$ 16.515 7.52 ---------------------------------------------------------------- WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental. ================================================================ Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)). ---------------------------------------------------------------- In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing. ---------------------------------------------------------------- WAGE DETERMINATION APPEALS PROCESS 1.) Has there been an initial decision in the matter? This can be: * an existing published wage determination * a survey underlying a wage determination * a Wage and Hour Division letter setting forth a position on a wage determination matter * a conformance (additional classification and rate) ruling On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed. With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to: Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to: Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue. 3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to: Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 4.) All decisions by the Administrative Review Board are final. ================================================================ END OF GENERAL DECISION